Q4 2026: 50MW

Location Details

DL-1: Delta, Nigeria

Behind the meter construction of 50MW hyperscale data center focused on Artificial intelligence workloads and High performance computing

Construction will be split in equal phases of 25MW and is primed for initial startup in Q4 2026

The land parcel is already acquired with a secure title, fencing is in progress and 133KVA overhead lines are situated on the property

The campus is 150meters away from the boundary of a 972MW gas fired power plant and 200meters from a major trunk highway with access to key network operator national backbone fiber infrastructure